Westfield Moss Point area:

Starting 9/5/2023 AT&T will be installing fiber optics.  The 24 hour emergency contact number is (330) 724-7730.  Southshore Cable will be the contractor.  Door hangers will be placed on the affected houses with contact information.  

Stearns Road

  • 10/20/2023 - Letter to Stearns Road residents regarding closure.
  • 09/25/2023 - REMINDER for Stearns Rd. traffic.
  • View the Stearns Closure Flyer (PDF) sent to residents.
  • The road is tentatively scheduled for closure on April 3, 2023, at 7:30 am. View the Detour Map (PDF).
  • The road is scheduled to reopen Southbound traffic only on September 14, 2023 ending August 2024. The current northbound detour will remain in place.
  • Stearns Road improvement “C.R.76” from Schady Road to Bagley Road
    • February 15, 2023: NTP (cannot close Stearns bridge until 4/1 at the earliest)
    • March 13, 2023: Tree clearing to start (1 week to complete)
    • April 7, 2023: Tentative Stearns bridge closure (after Jennings base repairs are done)
    • August 2, 2024: Part B – Stearns Road – substantially complete
    • September 29, 2024: Construction completion “anticipated”.